Category Archives: News

Winter Storm

The National Weather Service is forecasting a potentially crippling winter storm for portions of the mid-Atlantic Friday into early Saturday. If the storm causes power outages please report the outage to Dominion. You can report and check outages by clicking … Continue reading

Posted in News | 1 Comment

The Bridge is Open!!!

After 7 months and 5 days, the bridge is finally open.  The following is an update from our VDOT rep: +++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ There is some corrective work that will need to be done after the bridge is opened to traffic so … Continue reading

Posted in News, Uncategorized | Comments Off on The Bridge is Open!!!

Bridge Update #11

Update from VDOT: We met with the contractor earlier this week and I did request that they work as much night or weekend work that they could to get the bridge open to traffic.  At this point the remainder of … Continue reading

Posted in News | 3 Comments

Bridge Update #10

Neighbors – I received the following update from VDOT this evening: I just got out of a meeting with our construction staff and I expect a new two week look ahead later today or tomorrow but we do expect another … Continue reading

Posted in News | Comments Off on Bridge Update #10

Dominion Undergrounding Utilities Update

Neighbors – Several of you sent us questions for the Dominion rep.  We forwarded those along, and received the following replies (in blue): ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ Please forgive me for being so behind with my response.  Prior to Thanksgiving, I called around … Continue reading

Posted in News | Comments Off on Dominion Undergrounding Utilities Update

Bridge Update #9

I received the following update from our VDOT rep this morning: Although the December 3rd date has not been changed by the contractor, you can see our engineers assumed projection is closer to December 11th based on his response.  If … Continue reading

Posted in News | 1 Comment

Bridge Update #8

Late this afternoon I received an update from our VDOT rep: I received another update this morning putting the open date to Dec. 3rd due to the contractor receiving push back from their subs regarding work during the holiday week.

Posted in News | 1 Comment

Bridge Update #7

Received the following update this morning: The bridge open date has been moved to November 30th.  The contractor shows guardrail installation and sign installation that day.  If for some reason these do not get done we cannot open the bridge at … Continue reading

Posted in News | Comments Off on Bridge Update #7

Bridge Update #6

I received the following update from our VDOT rep: I just talked with our construction manager about the bridge opening.  Although the contractor has not submitted an update to the November 20th substantial completion date, we do not anticipate that … Continue reading

Posted in News | Comments Off on Bridge Update #6

Bridge Update #5

I requested an update yesterday, and received the following from our VDOT rep today: I received some information about the schedule.  At this time, we are supposed to have a new deck pour plan as of tomorrow.  This bridge opening … Continue reading

Posted in News | Comments Off on Bridge Update #5