Bridge Update #9

I received the following update from our VDOT rep this morning: Although the December 3rd date has not been changed by the contractor, you can see our engineers assumed projection is closer to December 11th based on his response.  If … Continue reading

Posted in News | 1 Comment

Bridge Update #8

Late this afternoon I received an update from our VDOT rep: I received another update this morning putting the open date to Dec. 3rd due to the contractor receiving push back from their subs regarding work during the holiday week.

Posted in News | 1 Comment

Bridge Update #7

Received the following update this morning: The bridge open date has been moved to November 30th.  The contractor shows guardrail installation and sign installation that day.  If for some reason these do not get done we cannot open the bridge at … Continue reading

Posted in News | Comments Off on Bridge Update #7

Bridge Update #6

I received the following update from our VDOT rep: I just talked with our construction manager about the bridge opening.  Although the contractor has not submitted an update to the November 20th substantial completion date, we do not anticipate that … Continue reading

Posted in News | Comments Off on Bridge Update #6

Bridge Update #5

I requested an update yesterday, and received the following from our VDOT rep today: I received some information about the schedule.  At this time, we are supposed to have a new deck pour plan as of tomorrow.  This bridge opening … Continue reading

Posted in News | Comments Off on Bridge Update #5

Follow Up Conversation with Dominion – Undergrounding Utilities

Neighbors – Below you will find a Dominion Power underground project update from Steve Burns.  As with all posts on our website, there is a comment section. We encourage you to leave comments on the post vs. sending emails to … Continue reading

Posted in News | Comments Off on Follow Up Conversation with Dominion – Undergrounding Utilities

Bridge Update #4

I received the following update from our VDOT rep today when I asked the status: I was just planning on sending updates as things change.  I can tell you that I spoke with the inspector yesterday and they are scheduled … Continue reading

Posted in Uncategorized | Comments Off on Bridge Update #4

Bridge Update

The following update was received from our VDOT rep today: I talked with our construction engineer this morning about the Broomley Road Bridge project.  The contractor has now submitted a schedule that shows a substantial completion date of November 13th.  … Continue reading

Posted in News | Comments Off on Bridge Update

Dominion Strategic Underground Project

Dominion Power is working on a Strategic Underground project in the Flordon Subdivision to convert the existing overhead power lines to underground.  This project will improve the reliability of your service by reducing outages and restoration times follow a major … Continue reading

Posted in News | Comments Off on Dominion Strategic Underground Project

Open House

Please join us for an Inside Ivy Garden Party!  We are so grateful to Mary Anne Burns for volunteering her lovely yard for a garden party! Grab a bottle of wine, a small plate of food or dessert to share and come … Continue reading

Posted in Uncategorized | Comments Off on Open House