Bridge Update #6

I received the following update from our VDOT rep:

I just talked with our construction manager about the bridge opening.  Although the contractor has not submitted an update to the November 20th substantial completion date, we do not anticipate that they will meet their date this Friday.  We are requesting an updated schedule and I will share as I get the information.

The VDOT construction manager said that he expects that it will be closer to the end of this month by the time the bridge is actually open to traffic.  I will send more information as I receive it.